House Update #3 -- 5 weeks of updates!

It is truly unbelievable how far we’ve come since our last update! It hasn’t even been 6 weeks and we’ve seen so much movement on the lot. We’ll take you through each step as we go through this post.

EFA3E686-F7EE-48C8-A1B0-259249637EAB.jpg

We broke ground!

We’re calling this first series, “the very boring dirt stuff”. I swear, this stuff took forever & as I was reflecting on this today I was realizing it’s because we weren’t really seeing much happen. So this stage felt like it went on and on and it would be forever until we saw our HOUSE go up. BUT these things are important! The first few weeks they…

-Poured concrete footings & crawl space walls

-Installed underground water & sewer lines

-Waterproofed & backfilled our foundation

966C6547-08D8-42EE-80DB-5F72F3E945F1.jpg

So we went out and saw a huge hole and that was super exciting. Literally, we were stoked for SOMETHING to be happening haha…

651593D3-A987-429E-ADEC-3B64ADB2171B.jpg
E589C8C9-D382-421D-ACE2-00FF22EC32B7.jpg

…and then eventually we saw the crawlspace take shape, until…

058D6044-A00B-4B71-87D8-B6FCDDF56329.jpg
E0CC8647-BAB9-4A06-84ED-C0BA0C665156.jpg

…our crawlspace was finished and ready to be built upon, here comes the fun stuff! Within the last week, we saw the last series of photos unfold ( O N E W E E K ).

…and this is where we ended the week! See that little bitty gable? I love it, it’s so cute. I can’t wait to take you guys inside. It is pretty surreal to walk the perimeter of the house, knowing we will be living there in 2 months! It’s seriously so peaceful in our backyard, the neighborhood is so much more quiet than I imagined and I took a moment to just stand there and take it all in. One day we’ll look back on these pictures and be all mushy about the time when our house was still being built & I can’t wait for that day.

So that’s where we’re at! I’m so excited to see our siding go up. We picked a pretty neutral palette of vanilla-y colors. The top left section of the house will be vertical siding/board & batten, and the rest of the house will be normal horizontal siding, as well as dark dark green shutters. But I think the board & batten will be such a cute touch :) This week they were supposed to be finishing our framing & work on our plumbing and HVAC lines. We should be having our pre-drywall meeting this coming week or next and then drywall goes up! I know we mentioned in our last post about our concerns about the backyard but now that the house is in place, I think it’s going to be really sweet. It’s definitely narrow, but really long (perfect for throwing sticks with Mia, haha). ANYWAYS, things are starting to move fast & we’re stockpiling furniture and decor. Can’t wait to share more as it unfolds!

1 Comment

Comment

House Update #2 -- Our pre-construction meeting

Howdie to all of you who are following along in our home building process! We really didn’t think we’d be posting another one of these updates for a few more weeks but today was a big day.

To give y’all some back story on today, we have felt a bit uneasy about one thing in this whole process. Everything has seriously been a dream, from our first meeting with our sales rep (Sharon) to getting approved and working with our loan officer (Liz), it has really been a blessing and so easy. If you read our last update, you know that we were walking into this thing a little nervous and gun shy. We have just been searching and pursuing so many different things that we were nervous that another door would be slammed in our faces. But God has been so faithful and has not only given us green lights, but you know that feeling when you’re driving on a road all alone, no one in the lanes next to you, green lights as far as you can see? Yeah, that’s how this feels. Such ease. But there was this one thing: our lot. When we arrived at our sales meeting in January, we knew they would only be opening up a few lots at a time. Ryan Homes likes to build in sections, so they only allow you to purchase a home on specific lots until they open the next section. Usually by then, the price on the home would go up. We knew we wanted to get in at the beginning price so we only had 5 or so options for lots. The one we chose was on the corner next to a retention pond (this will always remain this way so we can know for sure that we will never have neighbors on our right, so nice). We walked away so sure of our decision and so excited. But as I continued to pour over our lot and ya know, drive by and what not, I started to think, “it’s just not very big”. Will we have enough space in our backyard to fence in for Mia? Will we even have enough room for a patio? Where will the house go? I just couldn’t picture it. Our lot is verrrry wide (which means more space between us and our one neighbor), but a narrow area in the back that was making me nervous.

Cm2eCu25TbKgdvNPZMH6RA.jpg
DZmZ1bIESuOqZOZytI%c6Q.jpg

And we were also a little worried about the plan for water drainage since the back of our lot is sloping down towards the back of the house. So we set up the meeting to talk about our concerns, and while we were chatting about meeting, our project manager suggested rolling our “pre-construction” meeting into our time so we don’t have to come out twice (little does he know, I’m out there more than a few times a week haha).

When we arrived today, Justin (project manager) walked us to the lot and explained everyyyything that was happening with our lot. They had flagged the house site at this point too which was super helpful in seeing where our house would be and how much of the land it would take up.

IMG_7581.JPG

The front right flags are marking our driveway and corners of our garage. The left two flags and the back flags mark the corners and footprint of our house. There is definitely a narrow space between the black fencing and the back of our house but what I didn’t consider was the land that is behind the black fence is also ours. And there is a significant amount of space back there. They are also grading our land to have a “swale” which will direct any water away from our home. So we are SO happy & excited.

Back at the model home, we had our meeting where we just went through all the pre-construction details. He confirmed all of our upgrades and showed us things like: our electrical map for the house, color schemes, blue prints, where certain key items are located within the house, smart home features that they include, and our estimated dates. This is the part we were soooo surprised about!!! We had planned on them breaking ground in March. But Justin told us today that they surprisingly got our permits early and that they would be ready to break ground next week. WHAT. This pushes our completion date up from June to May. Freaking out just a little bit over here.

We will continue to update you guys & I’m excited to share our design plans once we finalize everything. The home is pretty cookie cutter so we’re taking a few weeks when we close to renovate certain areas and really give it the character we want it to have.